Denver International Airport South Anchorage Modifications -
Denver, CO
Architect: Parsons
Photo Credit: City and County of Denver
2016 Completion Date: N/A
Addition of a multi-level transit center and hotel required reconfiguration of existing masts and tie-backs. Temporary towers erected around the masts maintained the shape and prestress of the roof membrane while two exterior masts were lengthened and four anchorages replaced by new struts and cables. Severud Associates worked closely with the construction team on sequencing.